Before starting construction, you must obtain several No Objection Certificates (NOCs) from relevant authorities. These vary by city but commonly include:
1. Land Use Approval / Zoning NOC – Confirms commercial usage is allowed
2. Building Plan Approval – Submitted to CDA (Islamabad), LDA (Lahore), SBCA (Karachi), etc.
3. Environmental Impact Assessment (EIA) – For larger or multi-storey buildings
4. Fire Safety NOC – Issued by the local fire department
5. Utility NOCs – For electricity (e.g., WAPDA, K-Electric), gas (SSGC/SNGPL), and water
6. Height Clearance NOC – If near airports (from CAA)
Note: Incomplete documentation can delay approvals by months. Always consult a registered architect or town planner.