Before constructing or renovating a commercial property, you must get your building plans approved by the relevant city development authority:

  • Islamabad: Capital Development Authority (CDA)
  • Lahore: Lahore Development Authority (LDA)
  • Karachi: Sindh Building Control Authority (SBCA)

Steps for Approval:

  1. Hire a licensed architect to prepare site and building plans according to zoning laws.
  2. Submit documents including:
    • Ownership proof (Registry, Fard)
    • Lease or allotment letter (if applicable)
    • Site and architectural drawings
    • Structural stability certificate
  3. Pay processing and scrutiny fees.
  4. The authority will conduct a site inspection.
  5. If compliant, approval is granted, often within 30–60 days.

Tip: Plans must comply with floor area ratio (FAR), height limits, and parking requirements.